Safespan Europe Installs Largest-Ever
Safespan® Platform
on UK's Tinsley Viaduct
Sheffield, England / 06
March 2003 -- Safespan Europe and its installation partner CAN Ltd.
installed a Safespan® Multi-Span Bridge Platform System® in just 90
days on Sheffield's 2 km-long Tinsley Viaduct. The system
includes platforms under the viaduct's 20 m (65 ft ) high upper
Highway M1 roadways and the 10m (33 ft) lower Highway A631 eastern
roadway. CAN has also fitted the cabling system under the lower
western roadway. They will switch the platform modules from the
eastern side after work there is completed. By the end of the project,
Safespan expects to have some 750,000 ft2 (70,000m2) of platform
installed-- its largest project to date.
ClickHere
for Access International's
detailed coverage of this major installation.
Safespan Platform Systems, Inc. Establishes
Canadian Affiliate --
Begins Rainbow Bridge Project
Tonawanda, New York /
02 January 2003 - Tonawanda,
New York-based Safespan Platform Systems, Inc., has expanded its North
American marketing operations by appointing Skyway Canada, Ltd. as the
exclusive source for its labor-saving Safespan® Multi-Span Bridge
Platform System® throughout Canada. Skyway is a full-service
equipment distribution company whose products include a broad range of
scaffolding, heavy duty shoring, swing stages and safety fencing. In
addition to its two Metro Toronto locations, it operates distribution
centers in Sarnia, Ontario; Edmonton and Calgary, Alberta; and Kelowna,
BC. Skyway completed its first
installation of a Safespan cable-suspended platform and shielding
system on the Nelson River Bridge in British Columbiain 2001.
The company has several major bridge and building projects for
Safespan platforms pending in Ontario. Safespan
and Skyway are currently working together on their respective sides of
the international Rainbow Bridge over the Niagara River gorge. The
companies have jointly installed 19,602 m2 (211,000 ft2 )
of Safespan platform to conform with the steel arch and other bridge
components to provide continuous, safe access for the Clara Industrial
Services Ltd. crews metalizing and painting the famous structure. The
project will be completed in the summer of 2003
 |
| The Rainbow
Bridge project involves one platform under the roadway plus platforms both
above and below the arch. Use of Safespan's systesm provided safety, not only
for the employees rehabilitating the bridge, but also for passengers and crews
on the Maid of the Mist cruising the turbulent waters below. |
Safespan Busy Throughout the US New York, NY / 15 December 2002 --
Safespan, Inc. will have a very busy year furnishing its famous Safespan® Multi-Span Bridge Platform System on major bridge rehabilitation projects throughout the country. Several projects represent repeat business with satisfied contractor customers. Amount of Safespan Platform Used | Project/Contractor | Owner |
| 200,000 sf | Chicago Skyway Bridge Walsh Construction | City of Chicago Department of Transportation |
| 211,000 sf | Rainbow Bridge Clara Industrial | Niagara Falls Bridge Commission |
| 270,000 sf | Manhattan Bridge Koch Skanska | NYC/DOT |
| 500,000 sf | Tappan Zee Bridge L & L Painting | NYS Thruway Authority |
| 259,000 sf | Henry Hudson Bridge George Cambell Painting Co | TBTA
|
| 100,000 sf | Harlem River Lift Span Yonkers Contracting | TBTA |
| 100,000 sf | Golden Gate Bridge Marinship Construction | Golden Gate Bridge Authority |
| 50,000 sf | Oakland Bay Bridge Schimmick | Cal-Trans |
| 133,000 sf | Braga Bridge Mass. Highway | Mass Highway |
| 400,000 sf | St. Georges Bridge Aulson Painting | US Army Corps Of Engineers |
| 186,000 sf | William Preston Memorial Bridge Cianbro Corp. | Chesapeake Bay Bridge & Tunnel Authority |
 Safespan, Inc. Receives 2002 NOVA Award
Tonawanda, New York / 25 May 2002 -- Safespan, Inc.’s Multi-Span
Bridge Platform System has been honored with the 2002 NOVA Award. Instituted by
the Construction Innovation Forum in 1989, The NOVA Award recognizes innovations
that have made significant advances on construction, resulting in improved
quality and reduced costs. Lambros Apostolopoulos and David Malcolm accepted the
award at this year’s Innovation Celebration Banquet in Livonia, Michigan.
ClickHere
for more details
Safespan Products Speed Reconstruction Of The Niagara Falls Observation Tower
 Observation Tower Niagara Falls, NY | Tonawanda,
New York / 13 November 2001 - Both of Safespan, Inc.'s access
products are being used by the contractors reconstructing the famous observation
tower next to the American Falls in Niagara Falls, New York. The company has
deployed thousands of meters of its Plus Eight® Modular Scaffolding System to
provide the support for encapsulation and shielding to protect workers on the
tower from the elements during the harsh winter construction season. In
addition, 1,027 m2 (11,050 ft2) of Safespan's Multi-Span Bridge Platform
System® is furnishing secure access to the underside of the tower's observation
decks that are undergoing major rehabilitation. The company custom engineered
and installed the combined access system on a turnkey basis. The 180-foot (55 m)-tall steel structure provides not only a magnificent view of the entire bi-national attraction from its deck, but also elevator access to the U.S. dock for the historic Maid of The Mist tours that travel to the foot of the Canadian Falls. The Niagara Region is subject to 100-inch (2.5+ m) average snowfall each year, but the gorge has its own microclimate, generally making conditions worse than in the surrounding communities. The shrink-wrapped Safespan scaffold and platform system has already provided protection for workers from 50+ knot winds. Spray from the falls is expected to coat much or all of the structure with ice once the winter season begins, adding to the stress on the scaffolding. The fast-track reconstruction project is to be completed by April 2002.
 Safespan, Inc. Makes 2001 Inc. 500 List Tonawanda, New York / 19 October 2001--Five-year revenue growth of 681 percent has placed Safespan, Inc., of Tonawanda, NY 429th on the 20th Annual Inc. 500 list of America's Fastest-Growing Private Companies. The company provides secure access systems for bridge and industrial rehabilitation applications on a turnkey basis. Safespan's
2000 revenues reached $10.7 million and are continuing to grow at a rapid
pace. Founded by Lambros Apostolopoulos in 1995, the company's employment
grew from 20 in 1996 to 145 last year. In 2000, it expanded from its site at
252 Fillmore Avenue by acquiring and redeveloping nine acres of a nearby
facility.
ClickHere
for more details
Safespan Begins Work on Manhattan Bridge
 The Manhattan Bridge City of New York Manhattan-Brooklyn, NY | New
York, NY / 10 August 2001 -- Safespan is installing 270,000 sq. ft. of its
cable-suspended Multi-Span Bridge Platform System® to provide safe, secure
support for the Koch Skanska crews rehabilitating the Manhattan Bridge. This
toll-free East River crossing is 6,855 feet (2,089m) long and has seven
lanes of vehicular traffic plus four rapid transit tracks. Construction
began in October 1901 and the bridge opened to traffic the last day of 1909.
It is the newest of three the suspension bridges connecting downtown
Manhattan with downtown Brooklyn. The Manhattan Bridge was the first suspension bridge to be designed using deflection theory. It has four cables, each supporting a stiffening truss, and has spans of 725, 1470, and 725 feet. It is a major metropolitan artery with dense vehicular traffic. In addition, 276 trains cross each track on its north-side every weekday; while 135 trains per day cross in each direction on its south-side tracks. Safespan's system is projected to remain on the bridge until the fall of 2003.
Safespan Used Increasingly for Railroad ApplicationsTonawanda,
NY / 13 June 2001 -- Safespan's unique Multi-Span Bridge Platform System®
is being used for a growing number of railroad and transit bridge
rehabilitation and painting projects.  |  |  | Broadway Harlem River Bridge City of New York Manhattan-Bronx, NY | Jamaica Bay Swing Bridge Metropolitan Transit Authority Jamaica, NY | Rock Island Arsenal Bridge Rock Island Arsenal Rock Island, IL |
By
using Safespan's cable-suspended system on rail and dual rail-highway
bridges, both the rights-of-way, as well as vehicles and rolling stock are
completely protected from falling debris. Workers enjoy fast, secure access
and safe working conditions. The system is being installed on the historic
Manhattan Bridge in New York City that carries two heavy-rail transit tracks
in addition to roadways and bicycle/pedestrian pathways.

The Bridge Access Revolution Arrives in Europe Tonawanda, New York / 23 April 2001 - The Safespan Multi-Span Bridge Platform System® is set to revolutionize the European bridge painting and rehabilitation marketplace, as it has in the U.S.A. for the past six years. Tonawanda, New York-based Safespan, Inc., has appointed the Turner Group of Companies in Glasgow, Scotland as the exclusive source for its patented cable-suspended platform and shielding technology throughout Europe. Turner, which is well-known for its highly efficient Plus Eight® scaffolding systems, will serve the bridge rehabilitation market through its newly-formed company, Safespan Europe Ltd. Safespan Europe will supply the Safespan Multi-Span BridgePlatform System® primarily on a installed basis, employing the well-accepted turnkey technique that has proven so successful in the United States. The British Health and Safety Executive (HSE) recently assessed Safespan® platforms for use in the United Kingdom and found that, in addition to being fire resistant, they meet all of its other technical objectives. Safespan Europe intends to use HSE-registered and Safespan-approved installers to execute all its European contracts. After the introductory stage is completed, it should only be a matter of time until the unique Safespan® system becomes the primary form of structural access for bridge painting refurbishment throughout the U.K. and the rest of Europe. European enquiries about the cost-saving system should be addressed to: Safespan
Europe Ltd., 65 Craighton Road, Glasgow G51 3EQ, Scotland TEL: +44
(0) 141 440 0663 / FAX: +44 ( 0) 1414251073 E-mail: info@safespaneurope.co.uk. Enquiries
from England may be addressed to our Manchester office:Safespan
Europe Ltd., Unit 14, Clayton Industrial Estate, Louisa Street,
Openshaw, Manchester M11 1BR, England TEL:+44 (0)161 220 7467 / FAX:
+44 (0)161 2307732 E-mail: info@safespaneurope.co.uk. 
[ Contact Us ]

|
|
|