|
Safespan
Europe is installing an extensive underbridge access system on a major road
bridge in the the UK, and it is the first time that its patented technology
has been used outside the US. Access International's Lindsay Gale
reports from the site
Perfect
Platform
The M1 motorway, one of the UK's major north-south
transport arteries, cuts through the city of Sheffield and is carried for 1
kilometre of its route on a two-tier bridge, the Tinsley Viaduct, which also
supports parts of the A631 main road. With a combined length of just over two
kilometres, this structure was identified as requiring strengthening to cope
with current and projected traffic volumes, and an £85 million (US$131.5
million) three-year project is now underway.
A major problem faced by the contractor, Cleveland Bridge UK, was how to
provide access to the underside of both roadways while minimizing the
disruption to motorway traffic and surrounding city road, rail and tram
systems. Using traditional scaffolding was likely to cause major disruption
for an extended period while at the same time imposing undesirable, and
possibly unacceptable, physical loads on the structure itself.
A solution was found in the underbridge access system developed by Safespan in
the US and now being promoted in Europe through Safespan Europe, which was
established in 2001 as a trading division of Glasgow-based scaffolding
specialist Turner Access. After discussions with the client, the Highways
Agency, main contractor Edmund Nuttall and Cleveland Bridge, a letter of
intent was issued to Safespan Europe for the construction of working platforms
under the bridge that gave the company just six weeks for detailed
preparations before commencement of installation and for shipping necessary
components from Safespan's US manufacturing facility.
Safespan works closely with its preferred installation partner, CAN Limited,
who in the words of Robin Cochrane, Safespan Europe general manager,
"provides the high level of rope access skills that we require. The
combined team came on-site on 23rd August and just three months later has
completed the platforms under the 20 m(65 ft) high upper M1 roadways and the
10m (33 ft) lower A631 eastern roadways. CAN has also fitted the cabling
system under the lower western roadway to which the platform modules on the
eastern side will be switched once work there is completed. By the end of the
project, we expect to have installed some 750,000 ft2 (70,000m2) of
platform."
It has been a major undertaking for all involved; "At its peak, some 45
Safespan and CAN personnel were on site," says Mr. Cochrane, "but
once final assembly is complete, including total enclosure of the work areas
and the erection of access towers down each side of the viaduct, the site will
be handed over to the contractors and their work will commence. Once
completed, towards the end of 2005, Safespan and CAN will return to remove the
platforms."
So what has Cleveland Bridge gained from adopting Safespan's patented access
system? First, assembly time is an estimated 30 per cent less than for
traditional scaffolding solutions; simultaneous access has been gained to
multiple spans; disruption minimized; and the need for large storage areas
eliminated. The extremely light yet strong (2.5 kN/m2) Safespan® system also
minimizes the loads imposed on the structure itself while still being able to
support the heavy loads required on the platforms.
Once the side panels are installed, work areas will be fully encapsulated,
providing environmental protection during shot-blasting and painting
operations, and at the same time providing full protection to those below the
viaduct - a crucial benefit
given that two railway lines, a tramline and various roads run underneath.
Maximum headroom
The single most important advantage, however, is gained
from the fact that adequate clearance is provided below the upper platform to
allow the free flow of traffic on the lower roadways while still creating
adequate working headroom above.
Safespan's large open work areas that greatly assist inspection and the
controlled access to the platforms provided by the towers will also be a
positive boon in these security-conscious times. It will also provide a great
working environment. Apparently, two of the contractor's welders had sneaked
up to have a look at where they were going to be working and were heard to say
that it was the best work site they had ever seen.
Tinsley is a significant project for Safespan Europe, and the first since the
US company entered the European market in 2001. Robin Cochrane, who has lived
with the project from the very start, told Access International;
"This is the largest project that Safespan has ever tackled since its
establishment in 1995, and while the time-scales were extremely tight and the
project itself was very demanding, we are extremely proud of the final result.
We are certain that the success of this project will lead to further contracts
for the Safespan® system."
Discussions are currently underway on a number of future projects, with
Tinsley Viaduct expected to see a number of evaluation visits by potential
clients in the very near future. They are likely to be impressed.
Reprinted with the kind permission of KHL Group Ltd.,
publishers.
Back
to News
|